Preconstruction: Frequently Asked Questions
What does preconstruction mean in construction?+
Preconstruction is the planning phase before work starts on site. The contractor or construction manager budgets, estimates, checks the design for constructability, proposes value engineering, plans procurement and builds the schedule, so the owner can sign a price and a plan.
What does a preconstruction manager do?+
A preconstruction manager runs a builder's precon work on a project. They lead the estimate at each design stage, run constructability and value engineering reviews with the architect, line up subcontractors and long-lead orders, and present the budget or GMP proposal to the owner. On smaller teams the chief estimator often holds the role.
What are preconstruction services?+
They are the advice and pricing a builder provides during design, under contract and usually for a fee. In AIA A133-2019 they include a first check of the owner's program, schedule and budget, estimates at each design stage, constructability and cost advice, a project schedule, a subcontracting plan and a procurement schedule for items ordered before construction.
What is a preconstruction meeting?+
It is a kickoff held after the contract is awarded and before work starts. The owner, contractor and design team confirm who approves what, the schedule, submittals, safety, site rules and payment steps. On US federal contracts, FAR 36.212 has the contracting officer give the winning contractor a preconstruction orientation, by letter or at a preconstruction conference, covering items such as labor standards, subcontracting plans and who holds authority.
Who pays for preconstruction services?+
The owner, when precon is part of the contract. Under AIA A133-2019 the owner pays the construction manager for preconstruction phase services under Article 5, separate from the construction phase fee. On bid work, a contractor's estimating is usually its own overhead, recovered only through the jobs it wins.
Is preconstruction the same as estimating?+
No. Estimating is one part of preconstruction. Precon also covers budgeting against the owner's program, constructability review, value engineering, procurement planning and scheduling, and on a CM at risk job it ends with a guaranteed maximum price proposal.
How long does preconstruction take?+
As long as the design and the delivery method need. On a bid job it is the weeks between the invitation to bid and the bid date. On a CM at risk or design-build job it runs alongside design, from early concept to the guaranteed maximum price. Under AIA A133-2019 construction can even start before precon ends, on fast-track work.
Still measuring by hand? Your next takeoff can run while you review this one.
See it on your plansRelated Terms
Keep going: A Preconstruction Example: Bringing an Estimate Back to Budget, The construction bid process, step by step or explore Construction Estimating Software.
Figures on this page are illustrative. Construction estimates depend on project-specific conditions, source documents, market pricing, and professional judgment. Ruh's AI assists the estimator and does not replace professional review: your team reviews, validates, and approves every estimate, bid, and pricing decision.