100% money-backBook a walkthrough
For commercial concrete contractors

Concrete estimating software. Slabs, footings, and walls, priced on your numbers.

Concrete estimating software turns foundation and structural drawings into a priced concrete bid: footings counted from the schedule, slabs and walls measured, yards taken at the printed depths, rebar converted from the bar schedule, and every line priced on your own price files. Below, watch a foundation plan get measured, see a concrete budget priced and approved, and get a free takeoff on your own set.

Measuring first? Concrete Takeoff Software

Clients include

PCL Construction logoECC logoTaurus Builders logoAlliance Construction Solutions logo
Start with a free concrete takeoff

Send the foundation plans for one job. The takeoff comes back free, element by element, ready to price.

No card. Your estimator decides what happens next.

What you get
  • ✓Yards only from depths printed on the drawings
  • ✓Forms, ties, and steel carried by each element's assembly
  • ✓No proposal until your estimator approves the concrete budget

Construction companies working with Ruh

  • pcl logo
  • ecc logo
  • taurus logo
  • alliance logo
  • dondlinger logo
  • spyder logo
  • comstock logo
  • limbach logo
  • adf logo
  • gldd logo
  • orion logo
  • argan logo
Quick answer

Can concrete estimating and quoting software price on our own costs?

Yes. Ruh measures slabs, walls, and foundations, converts them to yards at the depths on the drawings, and prices every line on your own unit costs through 13 starting concrete recipes you can edit, before your estimator approves the quote. A 30 ft by 50 ft slab at 6 in is 27.8 cubic yards before waste.

in a 30 ft x 50 ft slab at 6 in, before waste
27.8 CY
concrete recipes to start from, yours to edit
13
on every takeoff, the second one blind
2 counts
Watch it measure

What happens before a concrete line is priced?

Ruh reads the foundation plan against the footing schedule and the structural notes, counts each spread footing and pier by mark, runs the continuous footings and grade beams by the foot, and measures the slab areas, so the yards behind the bid can be checked element by element.

Concrete takeoff on a sample foundation plan. The counts, areas, and lengths are sample figures, not a customer job.
  1. 1

    Spread footings and piers are counted by mark and sized from the footing schedule.

  2. 2

    Continuous footings and grade beams are run by the foot, and slabs are measured by area, with the depressed loading slab kept separate.

  3. 3

    Each element becomes a line in the concrete budget, still linked to its sheet. The grade beam steel waits: its bar schedule is on a sheet that was not sent.

The problem

Where concrete estimates come up short

Concrete estimates come up short in the conversions: square feet into yards at the right depth, bar spacing into tons, and the edges of every element into formwork.

Volume math across mixed elements

A slab, a spread footing, a pier, and a grade beam each convert to yards differently. One wrong depth, or a pier counted as a footing, and the order is short before the first truck.

Formwork that never makes the bid

Forms hide in the sections and details: both faces of a wall, slab edges, and the sides of every footing and beam. A volume-only takeoff leaves the form material and the carpenter hours out of the number.

Rebar conversions and splices

Reinforcing arrives as bar sizes and spacings and is bought by weight. Getting from #4 at 12 in each way to pounds per square foot to tons, with laps and dowels, is exactly where a tired estimator slips.

An estimator working through a takeoff across two monitors

Our view: A concrete estimate should show where every yard came from. When the depth, the area, and the bar spacing sit on the line beside the price, a reviewer can check a pour in a minute instead of rebuilding the takeoff to trust it.

Reference

What a concrete estimate is built from

A concrete estimate, Division 03 of the spec, starts from the elements on the foundation plan and builds the yards, forms, and steel from them. Each row names the sheet a quantity comes from and what the line prices on.

LineWhere the quantity comes fromUnitWhat it is priced on
Slab on gradePlan area at the thickness in the structural notesSF and CYReady-mix by the yard, place and finish per SF
Spread footings and piersCounted by mark, sized from the footing scheduleEA and CYReady-mix, forms, and crew per yard
Continuous footingsFooting runs on the foundation plan, size from the notesLF and CYThe footing assembly per foot
Foundation wallsWall length off the plan, height off the sectionsSF and CYThe wall assembly: concrete, forms both faces, ties, labor
Grade beamsBeam runs on the plan, size from the scheduleLF and CYConcrete, forms, and labor per foot
ReinforcingThe bar schedule, or the size and spacing in the notesLB or tonsRebar price and placing labor
FormworkEdges, faces, and sides of each elementSFCA or LFForm material, reuse, and carpenter hours
Vapor retarder and curingSlab areaSFYour price files
Pumping and finishing equipmentPours and slab areaDAY or HRYour equipment rates

Typical practice, not a standard. In Ruh, yards come only from depths printed on the drawings or given by your estimator, rebar weight only from a bar schedule or the noted size and spacing, and every rate from your price files, rate book, and quotes.

A worked slab and footing estimate

One 30 ft x 50 ft slab, 6 in thick, with #4 bars at 12 in each way, and 120 LF of continuous footing 16 in wide and 12 in deep.

Illustrative rates. In Ruh every rate comes from your own price files, and the yards come only from the depths printed on the drawings.

  1. 1
    Slab volume
    30 ft x 50 ft x 0.5 ft = 750 CF / 27 = 27.8 CY, plus 8 percent waste = 30 CY
  2. 2
    Footing volume
    120 LF x 1.33 ft x 1.0 ft = 160 CF / 27 = 5.9 CY, carried as 6.5 CY with waste
  3. 3
    Ready-mix
    36.5 CY x $172 = $6,278
  4. 4
    Slab rebar
    2 LF of #4 per SF x 0.668 lb per ft = 1.34 lb per SF, plus laps = 1.4 lb per SF; 1,500 SF x 1.4 = 2,100 lb = 1.05 tons x $2,400 installed = $2,520
  5. 5
    Place and finish
    1,500 SF x $2.10 = $3,150
  6. 6
    Slab edge forms
    160 LF x $4.50 = $720
Package total: $12,668 before markup, about $8.45 per SF of slab
Watch it price

How does a concrete takeoff become a priced bid?

The measured slabs, footings, and beams land in a budget grouped by trade. Yards come from the measured area at the printed depth, each line prices from your rate book, a price file, or a ready-mix quote, and the source stays on the line as it rolls up to the proposed bid.

  • ✓

    Yards from printed depths

    A slab or footing becomes yards only at a thickness printed on the drawings or given by your estimator, never a typical depth.

  • ✓

    Rebar from the bar schedule

    Reinforcing becomes a weight only from a bar schedule or the size and spacing in the notes. When the schedule is on a sheet that was not sent, the line waits.

  • ✓

    Ready-mix quotes stay quotes

    The ready-mix line waits unpriced until the supplier quote is entered, and keeps that quote as its source.

  • ✓

    Approval comes before the proposal

    Margin, overhead, fee, and contingency are yours, and no proposal is built until your estimator approves the concrete budget.

Concrete budget on sample figures. The ready-mix quote is keyed in by hand, as an estimator would.
How it works

From foundation plans to a priced concrete bid in three steps

  1. 1

    Send the drawings

    Foundation plans, structural sections, the footing and bar schedules, the structural notes, and any ready-mix quotes already in hand, as PDF or CAD.

  2. 2

    Ruh measures and prices

    Footings are counted by mark, beams and walls run, slabs measured by area, yards taken at the printed depths, and every line priced on your files with its source shown.

  3. 3

    Your estimator approves it

    Key in the ready-mix quote, change a waste factor or a markup, and approve. Yardages and priced lines export, and the proposal is built from the budget you approved.

A project engineer in a safety vest checking a tablet on an active site
Free takeoff

Price your next concrete bid from a free takeoff.

Send one foundation set. We return the takeoff at no cost so you can price it on your own numbers and see the yards, forms, and steel laid out element by element. Rather count by hand first? The concrete takeoff worksheet is a free CSV.

Your own drawings No card Your price book stays yours
From a customer

In a customer's own words

“Our estimators spent more time retyping quantities than thinking about scope. Ruh reads our drawings like a senior estimator and hands back a priced estimate we want to review, not rebuild.”
Director of Preconstruction, ADF GroupDirector of PreconstructionADF Group
faster bid turnaround
~50%
ADF Group, structural steel
on every takeoff, the second one blind
2 counts
Checks tab, before anything is priced
tied to the sheet it came from
Every line
Takeoff and price sheet
FAQs

Concrete estimating software FAQs

What concrete contractors ask before pricing a real bid with AI.

What is concrete estimating software?

Concrete estimating software prices a concrete bid from the drawings: slabs, footings, walls, and beams measured, converted to yards at the printed depths, reinforcing converted to weight, formwork and labor added, then markup. Ruh runs the concrete takeoff from your foundation plans and prices every line on your own price files, for commercial concrete contractors and foundation subcontractors.

Bring one concrete job. Check the yards yourself.

One foundation set, a free takeoff, and a 30-minute walk through the slabs, footings, and the budget they price into. If the yards do not hold up against yours, it cost you nothing.

Free takeoff No card 30-minute walkthrough
Start with a free concrete takeoff

No card. Your estimator decides what happens next.