Preconstruction and bidding guide

How to bid structural steel work as a subcontractor

Bidding structural steel comes down to three things: getting the tonnage right including connection material, drawing a hard line around what is structural steel and what is miscellaneous metals, and writing the exclusions down so the GC cannot level them onto you later. The number itself is the easy part. Most steel bids are won or lost on the scope boundary, not the price per ton.

Reading about it is slower than watching it. 30 minutes, your drawings.

Updated August 2026 · Reviewed by the Ruh construction team

Preconstruction and bidding work on a real project
Preconstruction and bidding

Start with what you are actually bidding

Before you weigh a single shape, settle the boundary. On most commercial jobs the steel package splits across separate MasterFormat sections, and the split is where money leaks:

  • 05 12 00 Structural Steel Framing. Beams, columns, base plates, connection material, the frame that carries load.
  • 05 21 00 Steel Joist Framing and 05 31 00 Steel Decking. Sometimes yours, sometimes a separate package, occasionally split between furnish and install.
  • 05 50 00 Metal Fabrications. Stairs, ladders, railings, embeds, lintels, bollards, pit frames, the long tail.

That last one is the single most common scope gap in steel bidding. Miscellaneous metals is a grab bag, it is drawn across architectural and structural sheets rather than in one place, and both the steel sub and the GC assume the other one has it. Decide explicitly whether you are carrying it, then say so in writing. A steel bid that is silent on misc metals is a steel bid the GC will assume includes misc metals.

The second boundary is furnish only versus furnish and erect. These are different businesses with different numbers. If you are furnishing only, the erector's crane, rigging, detailing coordination and site access assumptions are not yours, and your proposal has to say that plainly.

Read the drawings for your sheets, not the whole set

The set is large. Your scope is not spread evenly through it.

  • S-series structural drawings carry the frame: framing plans, column schedules, beam schedules, typical details, connection details.
  • Schedules beat plans. A column schedule tells you sizes, splices and base plate details far faster than scaling the plan. Read the schedule first, then use the plan for count and location.
  • Typical details are where the connection material hides. Stiffeners, gussets, doubler plates and shear tabs are rarely on the plans at all. They live in the details and they have real weight.
  • Architectural sheets carry your misc metals. Stairs and railings are drawn by the architect. If you only read the S sheets, you will miss the scope you are most likely to be held to.
  • Read the general notes and the specification section. Finish, bolt type, weld inspection and delegated design responsibility all live in the words, not the geometry.

Get the tonnage right

Tonnage drives the number, and bare shape weight is not tonnage.

Take off the frame by mark, get the linear footage or the count per mark, and apply the shape weight per foot. A wide flange beam is designated by nominal depth and weight per foot, so a W21x62 is 62 pounds per linear foot, and that is the easy half of the calculation.

Then add what the shapes alone do not include:

  • Connection material. Plates, angles, stiffeners, gussets, shear tabs, bolts. This is not a rounding error. Derive your percentage from your own shop's history on similar framing rather than from a rule of thumb you read somewhere, because it varies enormously between a braced frame and a simple-span job.
  • Base plates and embeds. Heavy, easy to miss, and often on a different sheet.
  • Moment connections. A moment connection costs materially more than a shear connection in both material and shop labour. Count them separately rather than averaging them into the frame.
  • Finish. Galvanizing versus shop primer versus bare steel is a large cost delta driven by exposure. Read the spec, do not assume.

Convert to tons at the end, and state the tonnage you carried in your proposal. See steel tonnage for how the conversion is handled and where it goes wrong.

The three things that blow up steel schedules

These are schedule risks, but they land on your price because the GC will ask you to own them.

  1. Shop drawing approval duration. Fabrication cannot start until shop drawings are approved, and approval is not in your control. State your assumed review turnaround as a number of working days in the proposal. If you leave it blank, you have accepted whatever the review actually takes.
  2. Delegated connection design. Many jobs push connection design to the fabricator's engineer. That is engineering cost, engineering schedule and engineering liability. If the drawings say connections are by the fabricator, price it and say you priced it.
  3. Anchor bolts and embeds arrive first. They are needed weeks before erection, they are usually installed by the concrete sub, and they are frequently supplied by you. Supply and install are two different scopes. See anchor bolt.

What the GC checks when leveling your bid

Bid leveling is the GC normalizing every steel proposal to one common scope so they can be compared. If you know what gets normalized, you can write a proposal that survives it. Expect them to check:

  • Tonnage carried, against the other bidders and their own estimate. An outlier gets a phone call, and if you cannot defend your tonnage you lose the job on credibility rather than price.
  • Misc metals, in or out, item by item.
  • Furnish only or furnish and erect, and if erect, whether crane and rigging are included.
  • Deck and shear studs. Metal decking and shear studs are classic split-scope items.
  • Who supplies anchor bolts and embeds.
  • Finish and inspection. Bolt grades, weld inspection, primer compatibility with fireproofing.
  • Unit prices for adds, so they can price changes without re-bidding.
  • Allowances you carried, and for what.

Anything you left silent gets filled in with an assumption, and the assumption will not favour you.

Structure the proposal so it cannot be leveled against you

A steel proposal that holds up has five parts, in this order:

  1. The number, with the tonnage and the scope sections it covers.
  2. Inclusions, listed as items rather than as a paragraph.
  3. Exclusions, listed the same way. This is the most valuable section in the document.
  4. Clarifications and assumptions. Shop drawing review duration, delegated design, crane access, laydown area, sequence, who supplies anchor bolts.
  5. Unit prices for the likely adds, so a change order is a lookup rather than an argument.

Price your markup on top of a cost you can defend line by line, and keep the takeoff that produced the tonnage. When the GC calls to level, the sub who can open the takeoff and show which sheet a quantity came from wins the conversation.

Where this fits

If you are on the other side of the table, leveling steel bids as the GC rather than submitting one, the same scope gaps read from the opposite seat. If you are running the takeoff itself, Ruh reads the drawing set, measures the frame, and prices the quantities against your own price book, with every line traceable back to the sheet it came from, which is exactly what you need when a GC questions your tonnage.

100%

Try Ruh on a real bid. 100% money-back guarantee if you are not satisfied.*

*Scoped delivery, terms apply. Read the guarantee terms

Start with a walkthrough

Frequently asked questions

What is the most common scope gap in a structural steel bid?+

Miscellaneous metals, section 05 50 00. Stairs, ladders, railings, embeds, lintels and bollards are drawn across architectural and structural sheets rather than collected in one place, so the steel sub and the GC each assume the other is carrying them. Decide explicitly whether misc metals is in your scope, list the items either way, and put it in writing. A bid that is silent on misc metals will be read as including them.

How do I work out steel tonnage for a bid?+

Take the frame off by mark, get linear footage or count per mark, and apply the weight per foot from the shape designation, so a W21x62 is 62 pounds per linear foot. Then add the material the shapes do not include: connection plates, angles, stiffeners, gussets, shear tabs, bolts, base plates and embeds. Derive the connection allowance from your own shop's history on similar framing rather than a generic percentage, because a braced frame and a simple-span job are not comparable. Convert to tons last, and state the tonnage you carried in the proposal.

Should I include erection in my steel bid?+

Only if you are asked to, and only if you say clearly which one you priced. Furnish only and furnish and erect are different businesses with different numbers, and a GC leveling bids will normalize them. If you are erecting, state whether crane, rigging, site access and laydown area are included, because those are the assumptions that get challenged. If you are furnishing only, say so at the top of the proposal, not in a footnote.

Who designs the steel connections, and why does it affect my price?+

It depends on the contract documents. Many projects delegate connection design to the fabricator's engineer rather than keeping it with the engineer of record. If the drawings say connections are by the fabricator, you are carrying engineering cost, engineering schedule and engineering liability, and you should price it and state that you priced it. Read the general notes and the specification section rather than inferring it from the details.

Still pricing in a spreadsheet? Your price book, automated end to end. Your estimator signs off.

See it run

Terms used in this guide

The estimating estimating cheat sheet
Every unit, waste factor, and conversion on one page. Free PDF.

Figures on this page are illustrative. Construction estimates depend on project-specific conditions, source documents, market pricing, and professional judgment. Ruh's AI assists the estimator and does not replace professional review: your team reviews, validates, and approves every estimate, bid, and pricing decision.