Construction glossary · Estimating Concepts

What is a bid alternate in construction?

A bid alternate is a priced option outside the base bid: an add alternate adds work or upgrades it, and a deduct alternate removes work for a credit. Below: add and deduct alternates in a table, a worked bid with one of each, our view, and a link to a free proposal template.

Free 30-minute walkthrough on your own drawings. No card.

Updated November 2026 · Reviewed by the Ruh construction team

The definition

Bid Alternate, Explained.

The owner lists the alternates in the bid documents so it can choose scope after it sees the prices. Each bidder prices the base bid and every alternate separately, and the owner accepts any mix of them in writing.

Alternates should carry the same overhead, fee and contingency as the base bid. A bare cost for an alternate understates it, and the owner who accepts it buys the work below cost.

To lay out the base bid and alternates for the general contractor, use the free construction bid proposal template.

How it is measured

A bid alternate is measured as its own price: an amount added to the base bid for an add alternate, or a credit off it for a deduct alternate, each with the same markups as the base bid.

Add Alternate vs Deduct Alternate

An allowance is different: a sum carried inside the base bid for work not yet defined.

Add alternateDeduct alternate
What it doesAdds or upgrades workRemoves work
PriceAdded to the base bidA credit off the base bid
ExampleLevel 5 finish in the lobbyDelete the corridor soffits

Our View

In our view, price every alternate as if it were the only change the owner accepts. Alternates priced as afterthoughts are where a good bid loses its margin.

Worked example

A Worked Bid With Alternates

Illustrative example. A drywall bid with overhead at 10 percent, fee at 8 percent and contingency at 3 percent, compounded in that order.

A $225,149.76 base bid with a $7,586.57 add alternate and a $4,282.74 deduct alternate: accepting both makes $228,453.59.

LineWorkingAmount
Base bid$184,000 direct with markups$225,149.76
Add alternate 1, Level 5 finish$6,200 marked up 22.364%$7,586.57
Deduct alternate 2, delete soffits$3,500 marked up 22.364%$4,282.74 credit

If the owner accepts both, the contract is $225,149.76 + $7,586.57 - $4,282.74 = $228,453.59.

Illustrative figures, not a customer job.

How Ruh handles it

How Ruh Handles Bid Alternate.

Try Ruh on a real bid.

Start with a walkthrough

Bid Alternate: Frequently Asked Questions

What is a bid alternate?+

A priced option outside the base bid that the owner can accept or decline after seeing the prices.

What is an add alternate?+

An alternate that adds or upgrades work, priced as an amount on top of the base bid.

What is a deduct alternate?+

An alternate that removes work, priced as a credit off the base bid.

Do alternates count toward the low bid?+

It depends on the bid documents, which should say. Some owners compare base bids alone, others the base bid plus the alternates they plan to accept.

Still measuring by hand? Your next takeoff can run while you review this one.

See it on your plans

Related Terms

Keep going: A Worked Bid With Alternates, the free construction bid proposal template or explore construction proposal software.

The Construction Estimating Cheat Sheet
Every unit, waste factor, and conversion on one page. Free PDF.

Figures on this page are illustrative. Construction estimates depend on project-specific conditions, source documents, market pricing, and professional judgment. Ruh's AI assists the estimator and does not replace professional review: your team reviews, validates, and approves every estimate, bid, and pricing decision.

Try Ruh on a Bid You Are Pricing Now.

Put Your Next Takeoff on Ruh.