What is a bid tabulation in construction?

A bid tabulation, or bid tab, is a table of the bids received for a project or trade package, set side by side so base bids, alternates and unit prices can be compared line by line. On this page: how a bid tab differs from bid leveling, a worked example where the low bidder changes, our view, and a free bid tabulation template.

Free 30-minute walkthrough on your own drawings. No card.

Updated November 2026 · Reviewed by the Ruh construction team

The definition

Bid Tabulation, Explained.

Public owners publish bid tabs after a bid opening, and general contractors build them to compare subcontractor bids.

A bid tab has one column per bidder and one row per priced item: the base bid, each alternate, unit prices, and checks such as addenda acknowledged and bond included. On public work, the owner reads bids aloud at the opening and posts the tabulation, often ranked from low to high, so every bidder can see the result.

Inside a general contractor, the bid tab is the first step of buyout and bid day. The second step, leveling, adjusts each bid for the scope it leaves out so the comparison is fair.

To tabulate and level subcontractor bids, use the free bid tabulation template.

How it is measured

A bid tab is read in dollars per bidder and in the spread between the highest and lowest bid. A wide spread usually means the bids are not pricing the same scope yet.

Bid Tabulation vs Bid Leveling

In typical practice, award decisions on private work are made on the leveled numbers, not the raw tab.

Leveling is covered in the bid leveling entry and the bid leveling guide.

Bid tabLeveled bids
ShowsWhat each bidder submittedEach bid priced to the same scope
GapsLeft as submittedFilled at the general contractor's plug values
Used forRecording and opening bidsChoosing who to award

Our View

A bid tab without a scope check is a list of prices, not a comparison. Confirm each bidder's exclusions before ranking anything.

Worked example

A Worked Bid Tabulation Example.

Illustrative example. The same office build-out package, tabulated as received and then leveled.

Bidder D is low as bid at $389,900 but leaves out $28,040 of scope, so it levels to $417,940. Bidder B levels to $406,300 and is the low leveled bid.

BidderAs bidLeveled
Bidder A$412,000$417,040
Bidder B$398,500$406,300
Bidder C$421,300$421,300
Bidder D$389,900$417,940

On the raw tab, Bidder D looks low by $8,600. It left out six items worth $28,040 at the general contractor's values, so $389,900 + $28,040 = $417,940, third of four. The spread falls from $421,300 - $389,900 = $31,400 to $421,300 - $406,300 = $15,000.

Sample figures from the free bid tabulation template, not a customer job.

How Ruh handles it

How Ruh Handles Bid Tabulation.

Try Ruh on a real bid.

Start with a walkthrough

Bid Tabulation: Frequently Asked Questions

What is a bid tab in construction?+

A bid tab is a table of all bids received for a project or package, with each bidder's base bid, alternates and other prices side by side.

Where can I find public bid tabulations?+

Public owners such as state transportation departments, cities and school districts usually post bid tabulations on their procurement pages after each bid opening.

What is the difference between a bid tab and a bid leveling sheet?+

A bid tab shows bids as submitted. A bid leveling sheet adjusts them for scope differences so they can be compared on the same work.

Who prepares a bid tabulation?+

The owner or its agent on public work, after the bid opening. On private work, the general contractor's estimator prepares one for each trade package.

Why is the lowest bid on a bid tab not always the best?+

Because a low number often reflects missing scope, an unacknowledged addendum or a heavy list of exclusions. Leveling shows what the bid costs once those gaps are filled.

Still measuring by hand? Your next takeoff can run while you review this one.

See it on your plans

Related Terms

Keep going: A Worked Bid Tabulation Example., the free bid tabulation template or explore Construction Estimating Software.

The Construction Estimating Cheat Sheet
Every unit, waste factor, and conversion on one page. Free PDF.

Figures on this page are illustrative. Construction estimates depend on project-specific conditions, source documents, market pricing, and professional judgment. Ruh's AI assists the estimator and does not replace professional review: your team reviews, validates, and approves every estimate, bid, and pricing decision.

Try Ruh on a Bid You Are Pricing Now.

Put Your Next Takeoff on Ruh.