100% money-backBook a walkthrough
Construction glossary · Sitework

What is silt fencein construction?

A silt fence in construction is a temporary sediment barrier made of woven geotextile fabric supported by posts and trenched into the ground along the downslope edges of a disturbed area. It slows runoff and traps sediment on site before it reaches inlets, streams, or neighboring property. Estimators measure it in linear feet (lf) installed, and a complete price also carries maintenance during the project and removal at final stabilization.

Free 30-minute walkthrough on your own drawings. No card.

Updated June 2026 · Reviewed by the Ruh construction team

Measured in linear feet (lf)Buried toe 6 in down, 6 in overLives on ESC plan sheetComplete line install + maintain + remove

How silt fence is measured in section

Geotextile fabric on postsGround line / gradeTrenched toe, backfilledToe 6 in deep, 6 in horizont…Run measured in lf along alignment
The definition

Silt fence, explained.

Silt fence is usually the largest single line in the erosion control package, drawn as a labeled line symbol along the downslope perimeter on the erosion and sediment control sheets of the civil set. The detail sheet governs what the unit price has to cover: post type and spacing, fabric height, and the toe of fabric trenched into the ground and backfilled so runoff cannot run underneath. The grading contractor or a SWPPP subcontractor installs it as one of the first activities on site, often right behind clearing and grubbing. New estimators get three things wrong. They price only the install and miss maintenance and removal, which the permit requires. They miss that wire-backed (reinforced) silt fence, called out where flows concentrate, costs meaningfully more than standard fence. And they take off the perimeter as drawn without checking the phasing notes, which can require fence to be relocated or reinstalled as grading moves across the site.

How it is measured

Silt fence is measured in linear feet along the installed alignment, taken off the ESC plan sheet. Carry separate lines for standard and wire-backed fence, because the detail and the unit cost differ. Add length for overlaps at joins and turns, typically a few percent. The pay items behind the lf are install (trenching or machine slicing, posts, fabric), maintenance (sediment cleanout and section replacement over the project duration), and removal with trench restoration at final stabilization. The big cost drivers are installation method (machine-sliced is faster than hand-trenched), soil and terrain along the alignment, and how many months the fence has to be maintained.

Worked example

A worked silt fence example.

Worked example

Net perimeter2 x (400 + 300) = 1,400 lf - 30 lf = 1,370 lf
With overlaps1,370 x 1.05 = 1,438.5, carried as 1,440 lf
Install (illustrative)1,440 lf x $4.25 = $6,120
Maintenance + removal (illustrative)144 lf x $4.25 = $612; 1,440 lf x $0.90 = $1,296
Complete line (illustrative)$6,120 + $612 + $1,296 = $8,028
How Ruh handles it

How Ruh handles silt fence.

100%

Try Ruh on a real bid. 100% money-back guarantee if you are not satisfied.*

*Scoped delivery, terms apply. Read the guarantee terms

Start with a walkthrough

Silt fence: frequently asked questions

How deep is silt fence buried?+

Typical details call for the bottom of the fabric to be trenched in about 6 inches deep and 6 inches horizontal (an L-shaped toe), then backfilled and compacted so runoff cannot pipe underneath the fence. Machine-sliced installation cuts a narrow slot and pulls the fabric in, achieving the same embedment faster. Fence laid flat on grade without a buried toe fails inspection and fails in the first storm.

What is the difference between silt fence and wire-backed silt fence?+

Standard silt fence is geotextile fabric stapled or wired to posts. Wire-backed (reinforced) silt fence adds welded wire or field fence behind the fabric and typically heavier posts, so it can hold up where runoff concentrates or where ponding loads the fabric. Designers call it out at low points, channel crossings, and below steep slopes. It carries a higher unit cost, so take it off as a separate lf line rather than blending it with standard fence.

When does silt fence get removed?+

After the area draining to it reaches final stabilization under the project's stormwater permit, typically meaning established vegetation or completed hard surfacing. Removal includes pulling posts and fabric, disposal, removing accumulated sediment (most specs require cleanout whenever sediment reaches about one third to one half of the fence height), and restoring the trench line. It is a real pay item, and forgetting it is one of the most common erosion control estimating misses.

Still measuring by hand? Your next takeoff can run while you review this one.

See it on your plans

Related terms

Keep going: read the full guide or explore AI construction takeoff and estimating software.

The Sitework estimating cheat sheet
Every unit, waste factor, and conversion on one page. Free PDF.

Figures on this page are illustrative. Construction estimates depend on project-specific conditions, source documents, market pricing, and professional judgment. Ruh's AI assists the estimator and does not replace professional review: your team reviews, validates, and approves every estimate, bid, and pricing decision.

100% money-back guarantee

Try Ruh on a bid you are pricing now.

Put your next takeoff on Ruh.