Look-Ahead Schedule: Frequently Asked Questions
What is a 3-week look-ahead schedule?+
It is the version of the plan the field works from: only the activities starting or running in the coming three weeks, with the constraints on each one listed and cleared.
Who prepares the look-ahead schedule?+
The general contractor's superintendent, usually with the project manager, and the foremen of each trade review and commit to it at the weekly meeting.
How far ahead should a look-ahead schedule go?+
Three weeks is the most common window on building jobs. Last Planner teams often use three to six weeks, longer when long-lead material is involved.
What is percent plan complete?+
Percent plan complete (PPC) is the share of activities planned for a week that were finished as planned. 8 finished of 10 planned is 80 percent.
How is a look-ahead different from a master schedule?+
The master schedule covers the whole job and changes rarely. The look-ahead covers the next few weeks, changes every week, and focuses on what each activity needs to start.
Still measuring by hand? Your next takeoff can run while you review this one.
See it on your plansRelated Terms
Keep going: A Worked Look-Ahead Example., the free construction schedule template or explore General Contractor Software.
Figures on this page are illustrative. Construction estimates depend on project-specific conditions, source documents, market pricing, and professional judgment. Ruh's AI assists the estimator and does not replace professional review: your team reviews, validates, and approves every estimate, bid, and pricing decision.