Critical Path Method: Frequently Asked Questions
What is the critical path in construction?+
The sequence of activities with zero total float. In the example above it is A, B and D, which is why a day lost on B costs a day at the end and a day lost on C does not.
What is float in a construction schedule?+
Float is the time an activity can slip without delaying the project finish (total float) or the next activity (free float). Activities on the critical path have zero total float.
Who invented the critical path method?+
Morgan Walker of DuPont and James E. Kelley Jr. of Remington Rand developed it in 1957. Their first paper on it was published in 1959.
Can the critical path change during a project?+
Yes. If a non-critical activity slips by more than its float, it joins the critical path and the old path gains float. Updating the schedule regularly shows when that happens.
Can you do CPM scheduling in Excel?+
Yes, for simple finish-to-start schedules, using the WORKDAY function and predecessor lookups. Lags, overlaps and large networks need scheduling software.
Still measuring by hand? Your next takeoff can run while you review this one.
See it on your plansRelated Terms
Keep going: A Worked Critical Path Example., the free construction schedule template or explore General Contractor Software.
Figures on this page are illustrative. Construction estimates depend on project-specific conditions, source documents, market pricing, and professional judgment. Ruh's AI assists the estimator and does not replace professional review: your team reviews, validates, and approves every estimate, bid, and pricing decision.