A scope sheet lists every item of work in one trade package and marks each line included, excluded or by others, with the drawing sheet or spec section it comes from. Build yours below, load the worked drywall example to see how it reads, and download it as a CSV file.

Reviewed by the Ruh construction team · November 2026

  • One line per item
  • Every line cites a sheet or spec section
  • Included, excluded or by others

Built with the free scope of work template at ruh.ai

Updates as you type

Build Your Scope Sheet

8 lines · Drywall · Illustrative example, change any line

Fill in the project header, then add one row per scope item. Every row needs a status and a drawing or spec reference, so nothing on the sheet rests on memory.

Project header

Mark every line

  • Included priced in this package
  • Excluded not in this price
  • By others name the party

Your scope sheet

Scope lines
8
Included
5
Excluded
1
By others
2
No drawing or spec reference0

Every line cites a drawing sheet or spec section.

Built in your browser. Nothing is uploaded, and Ruh keeps no copy.

Scope lines

One item per line, grouped by CSI section. Click any cell to edit it.

8 lines
#Trade or CSI sectionScope itemStatusDrawing or spec referenceNotesClarificationsApprovedRemove
1
2
3
4
5
6
7
8
How the CSV File Is Built

The page builds the file in your browser from the rows on screen. Nothing is uploaded, and Ruh keeps no copy. The file opens in any spreadsheet program: the project header comes first as field and value pairs, then one blank row, then one row per scope line with all seven columns.

Your rows are kept in this browser so a refresh does not wipe them, and Clear sheet removes them. The file is named after the trade and the date, for example scope-sheet-drywall-2026-11-03.csv.

That answers one scope sheet. Get a takeoff on your own drawings, free.

Send one set of drawings from a job you are bidding and we take it off free, every quantity tied to the sheet it came from.

The takeoff screen on a sample electrical sheet.
See AI takeoff and estimating

No card. Your estimator decides what happens next.

What Goes on a Scope Sheet

A scope sheet has six working columns: the trade or CSI section, the scope item, its status, the drawing or spec reference, notes, and clarifications. The status and the reference do the real work, because they decide who prices the item and where to look when someone disagrees.

A scope sheet is the line-by-line form of a trade's scope of work. Group rows by section so the sheet reads like the spec book, using CSI MasterFormat.

ColumnWhat to writeExampleCommon mistake
Trade or CSI sectionThe spec section the line belongs to09 29 00 Gypsum boardA trade name with no section, so nobody can find it in the spec book
Scope itemOne item of work, in plain wordsLevel 5 finish at lobby feature wallTwo items on one line, joined with and
StatusIncluded, excluded or by othersBy othersLeaving it blank and deciding at bid time
Drawing or spec referenceThe sheet or section the item comes fromA-601 finish schedule, 09 29 00No reference, so the line rests on memory
NotesQuantities, locations and conditionsLobby onlyNotes that change the price but sit in an email
ClarificationsAssumptions you state and questions for the design teamOther areas Level 4Assumptions nobody wrote down

A Worked Drywall Scope Sheet

Here is an illustrative drywall scope sheet for an office fit-out, eight lines long. Load it into the tool above and change it to fit your job.

Illustrative example
Trade or CSI sectionScope itemStatusDrawing or spec referenceNotesClarifications
09 22 16 Non-structural metal framingMetal stud framing for partition types P1 to P6IncludedA-501 partition types, A-101 floor plan, 09 22 16Deflection track at deck on rated wallsNon-rated partitions stop 6 in above the ceiling unless A-501 shows full height
09 29 00 Gypsum board5/8 in Type X board, Level 4 finish typicalIncludedA-501, 09 29 00Both faces unless the partition type shows oneFinish levels per Gypsum Association GA-214
09 29 00 Gypsum boardLevel 5 finish at lobby feature wallIncludedA-601 finish schedule, 09 29 00Lobby onlyOther areas Level 4
07 21 00 Thermal insulationAcoustic batt in partition types P2 and P4IncludedA-501, 07 21 00Full height of the stud cavity
07 84 00 FirestoppingHead-of-wall joints at rated partitionsIncludedA-501 rated wall details, 07 84 00Joint systems listed on A-501Penetrations firestopped by the trade that makes them
06 10 00 Rough carpentryIn-wall blocking for casework, grab bars and wall-mounted equipmentBy othersA-501 general note 6, 06 10 00GC marks locations before boardWho furnishes and installs: GC carpentry, confirm in the invitation
08 31 13 Access doors and framesFurnish and install access panels in gypsum boardBy othersM and P sheets, 08 31 13Mechanical and plumbing trades furnish and installLocations per the M and P sheets, confirm in the invitation
09 91 23 Interior paintingPrime and paint gypsum boardExcluded09 91 23Painting packageBoard left ready for paint at the specified finish level

Illustrative example. Sheet numbers and sections follow a typical commercial set.

Count board, studs and track for the included lines with the drywall calculator.

Included, Excluded or By Others: How to Mark Each Line

Mark a line included when your price covers it, excluded when nobody on your side will do it, and by others when you know another party does. "By others" only helps when the sheet names who the others are.

Included

Priced in this package, nothing more to say.

Excluded

Not in this price. Say why in clarifications if it is unusual.

By others

Name the party: GC, owner or the mechanical trade. A by-others line with no name is how an item falls between two packages.

  • Furnish and install can split. Write both in the notes, for example furnished by mechanical, installed by drywall.
  • If the documents carry an allowance for the item, say so in the notes.
  • After each addendum, re-check the rows it touches and add the addendum number to the reference.

The Boundary Items Every Trade Should Decide

Most scope arguments start at the edges of a package, not in the middle. These eight items sit between trades on almost every commercial job, so give each one a line and a status before you price.

Boundary itemTrades that often both expect the other to do itWhere it is usually specified
In-wall blockingDrywall, carpentry, casework, the trade hanging the itemDivision 06 rough carpentry, partition notes
FirestoppingDrywall and each MEP trade07 84 00, rated wall details
Access panelsDrywall and the MEP trade that needs access08 31 13, M and P sheets
Joint sealantsDrywall, glazing, painting07 92 00
Hoisting and liftsEvery trade and the GCDivision 01 temporary facilities
Cleanup and debrisEvery trade and the GC01 74 13 progress cleaning
LayoutTrade and GC surveyDivision 01, the subcontract
Patch and repair after other tradesDrywall, painting, the trade that cut the wallOften nowhere, which is the point

The Add boundary items button in the tool adds these eight rows with the status left blank.

Opinion. The view of the Ruh estimating team, not a measured result.

What Estimators Get Wrong About Scope Sheets

In our view, the most common mistake is a scope sheet that copies the spec table of contents and calls it a scope. A list of sections tells a bidder where to look, not what they are pricing.

  1. 01

    A line with no reference is an opinion.

    If it cannot point to a sheet or a section, a reviewer cannot check it.

  2. 02

    "By others" without a name.

    The other trade reads the same words and assumes it is yours.

  3. 03

    One sheet for every job.

    Boundary lines change with each set, so the sheet is rebuilt from the current drawings.

  4. 04

    Clarifications hidden in an email.

    If an assumption matters to the price, it belongs on the line it changes.

What This Template Cannot Do

The template organizes a scope you have already read out of the documents. It does not read the drawings, check that a reference is correct, or tell you whether an item belongs to your trade.

  • It does not measure quantities. Pair it with a takeoff or a trade calculator.
  • It does not know your subcontract. The subcontract and its scope exhibit decide what is binding.
  • It does not compare bids. Comparing sub bids on a common scope is bid leveling.
  • It is not legal advice.

How Ruh AI Fits Into Scope

A person on your team approves every scope line before Ruh measures it, and can edit every quantity and price.

  • Ruh AI's Takeoff Agent measures the approved scope, and withholds a figure when a sheet has no scale instead of guessing.
  • Ruh AI's Estimating Agent prices from your own rate book and history.
  • Each stage is approved before the next opens.

Scope of Work Template FAQs

Is the scope of work template free?+

Yes. Build the sheet on this page and download it as a CSV file with no sign-up, then use it on as many jobs as you like.

What format is the download?+

A CSV file built in your browser from the rows on screen, and it opens in any spreadsheet program. Your rows stay in your browser.

What is the difference between a scope sheet and a scope of work?+

The scope of work is the full description of what a contract or package covers. A scope sheet is that scope broken into one line per item, each with a status and a reference. See the scope of work glossary entry for the full definition.

Who fills in the scope sheet, the GC or the subcontractor?+

Either. A GC estimator writes one per trade package to send with the invitation to bid, and a subcontractor writes one to show exactly what the price covers. Both versions work best when they cite the same sheets and sections.

How detailed should each scope line be?+

One item per line, specific enough that someone can find it on the drawings from the reference alone. If a line needs the word "and" twice, split it.

Can I use the scope sheet to compare subcontractor bids?+

It gives you the common scope to compare against, which is the first step. The comparison itself is bid leveling, covered in the bid leveling glossary entry.

Bring the scope. Ruh measures what a person on your team approves.

Send one set of drawings from a job you are bidding and see the takeoff on your own sheets.

More tools: Pay Application Template and Drywall Calculator. All calculators

The example on this page is illustrative. Your drawings, specifications and subcontract decide what is in scope, and a person on your team approves every scope line.