What is an OAC meeting in construction?

An OAC meeting is the regular progress meeting between the owner, the architect and the contractor on a construction project. On this page: what a standing agenda covers, a worked example of an action log, our view, and a free meeting minutes template.

Free 30-minute walkthrough on your own drawings. No card.

Updated November 2026 · Reviewed by the Ruh construction team

The definition

OAC Meeting, Explained.

An OAC meeting reviews schedule, RFIs, submittals, change orders, safety and owner decisions, and every open item leaves with a name and a due date in the minutes.

OAC stands for owner, architect, contractor, the three parties to most building contracts. The meeting is where the people who can decide things meet often enough to keep the job moving: the owner answers its open questions, the architect works through design questions, and the contractor reports progress and raises what is blocking it.

Most building projects hold one weekly or every two weeks during construction, often run and minuted by the general contractor's project manager. Engineers, key subcontractors and the owner's consultants join when their items are on the agenda.

To run the minutes and carry items forward, use the free construction meeting minutes template.

How it is measured

An OAC meeting is judged by its action log: how many items are open, how many are overdue, and how long the oldest one has been carried. Item numbers that combine the meeting and the item, such as 4.03, make the age of an item visible.

What an OAC Meeting Agenda Covers

A standing agenda keeps the meeting short: review of the last minutes, safety, schedule and the coming weeks, open RFIs and submittals, change orders, owner items, quality, payment, and the next meeting date.

Most of the open items come from the RFI, submittal and change order logs, and the schedule review often uses a look-ahead schedule.

Our View

An item carried through three meetings needs a decision, not another week. Escalate it by name.

Worked example

A Worked OAC Meeting Example.

Illustrative example. Meeting 6 on an office build-out, held October 29, 2026: five attendees invited, four present, eight items on the agenda.

Meeting 6, eight items: three closed, five open or new, two overdue. Item 4.03 has been carried since meeting 4.

ItemOwner of the actionDueStatus
4.03 RFI 015 answerArchitectOct 27Open, overdue
5.04 Door hardware resubmittalGeneral contractorNov 4Open
6.01 Schedule updateContractorNov 5New
6.02 Rated corridor wall change requestOwnerNov 3New
6.04 Furniture delivery dateOwnerOct 28Open, overdue

Of eight items, three closed during the meeting and five stay open or new. Two are overdue, and item 4.03 has now been carried for three meetings, which is the one to escalate.

Sample minutes from the free meeting minutes template, not a customer job.

How Ruh handles it

How Ruh Handles OAC Meeting.

Try Ruh on a real bid.

Start with a walkthrough

OAC Meeting: Frequently Asked Questions

What does OAC stand for in construction?+

Owner, architect, contractor. An OAC meeting is the regular project meeting among those three parties.

Who runs the OAC meeting?+

Usually the general contractor's project manager, who sets the agenda and writes the minutes. Some contracts give the minutes to the architect.

How often are OAC meetings held?+

Weekly or every two weeks during construction on most building projects, with the frequency set at the preconstruction meeting or in the contract.

What is the difference between an OAC meeting and a subcontractor meeting?+

The OAC meeting is among the three contract parties and covers decisions. The subcontractor or foreman meeting is run by the general contractor and covers coordination and the look-ahead.

Who attends an OAC meeting?+

The owner or its representative, the architect, and the general contractor's project manager and superintendent, plus engineers and key subcontractors when their items are up.

Still measuring by hand? Your next takeoff can run while you review this one.

See it on your plans

Related Terms

Keep going: A Worked OAC Meeting Example., the free meeting minutes template or explore General Contractor Software.

The Construction Estimating Cheat Sheet
Every unit, waste factor, and conversion on one page. Free PDF.

Figures on this page are illustrative. Construction estimates depend on project-specific conditions, source documents, market pricing, and professional judgment. Ruh's AI assists the estimator and does not replace professional review: your team reviews, validates, and approves every estimate, bid, and pricing decision.

Try Ruh on a Bid You Are Pricing Now.

Put Your Next Takeoff on Ruh.