Schedule of values template

A schedule of values splits the contract sum into lines of work, each with a dollar value, and every payment request on the job is checked against it. Build yours here at contract award, by CSI division or your own cost codes, and download a CSV file that balances to the contract sum.

Reviewed by the Ruh construction team · November 2026

  • Lines by CSI division or cost code, with each line's scheduled value and share of the contract
  • A balance check that shows the difference from the contract sum until it reaches zero
  • An option to spread your fee and overhead across the work in proportion to cost

Built with the free schedule of values template at ruh.ai

Balances as you type

Contract Details

The contract sum is the number every line has to add up to.

Your schedule of values

Total of lines
$1,380,000
Contract sum
$1,380,000
Difference
$0

Balanced

Your costs total $1,230,000. $150,000 is spread across $1,200,000 of lines, a factor of 12.5 percent. $30,000 stays at cost.

Built in your browser. An unbalanced file downloads marked as a draft.

Schedule of Values Lines

Enter each line's cost. Scheduled values are worked out for you. Press Enter in a row to add one under it.

#CodeDescription of workCostAt costScheduled valueShareRetainage %NotesMove or remove
1Cost code or CSI divisionDescription of workCost ($)Keep at costScheduled value ($)$108,000.00Share of contract7.83%Retainage (%)Notes
2Cost code or CSI divisionDescription of workCost ($)Keep at costScheduled value ($)$30,000.00Share of contract2.17%Retainage (%)Notes
3Cost code or CSI divisionDescription of workCost ($)Keep at costScheduled value ($)$225,000.00Share of contract16.30%Retainage (%)Notes
4Cost code or CSI divisionDescription of workCost ($)Keep at costScheduled value ($)$180,000.00Share of contract13.04%Retainage (%)Notes
5Cost code or CSI divisionDescription of workCost ($)Keep at costScheduled value ($)$72,000.00Share of contract5.22%Retainage (%)Notes
6Cost code or CSI divisionDescription of workCost ($)Keep at costScheduled value ($)$126,000.00Share of contract9.13%Retainage (%)Notes
7Cost code or CSI divisionDescription of workCost ($)Keep at costScheduled value ($)$90,000.00Share of contract6.52%Retainage (%)Notes
8Cost code or CSI divisionDescription of workCost ($)Keep at costScheduled value ($)$189,000.00Share of contract13.70%Retainage (%)Notes
9Cost code or CSI divisionDescription of workCost ($)Keep at costScheduled value ($)$99,000.00Share of contract7.17%Retainage (%)Notes
10Cost code or CSI divisionDescription of workCost ($)Keep at costScheduled value ($)$135,000.00Share of contract9.78%Retainage (%)Notes
11Cost code or CSI divisionDescription of workCost ($)Keep at costScheduled value ($)$126,000.00Share of contract9.13%Retainage (%)Notes
Contract sum
$1,380,000
Total of lines
$1,380,000
Difference
$0

Balanced

How the Spread Is Calculated

In cost mode, the amount to spread is the contract sum minus the costs of every line. Lines ticked Keep at cost stay at cost, and each other line is raised by the same factor: amount to spread divided by the cost of the spread lines. Each value is rounded to the cent, and any cent left over goes to the largest spread line, so the total equals the contract sum exactly.

Each line's share is its scheduled value divided by the contract sum. Shares are rounded to two decimals, so they can add to 99.99 or 100.01 percent while the dollars balance. The total share is worked out from the totals.

That answers one schedule of values. Get a takeoff on your own drawings, free.

Send one set of drawings from a job you are bidding and we take it off free, every quantity tied to the sheet it came from.

The takeoff screen on a sample electrical sheet.
See AI takeoff and estimating

No card. Your estimator decides what happens next.

A schedule of values is only as good as the estimate under it. The estimate starts with the takeoff.

Book a walkthrough

How to Build a Schedule of Values

Start from the estimate that won the job. Roll its cost codes up into lines whose progress can be seen in the field, carry fee and overhead either as their own lines or spread across the work, and make the lines add up exactly to the contract sum.

  1. 1Enter the contract sum. It goes in Contract sum, at the top of the contract details.
  2. 2Choose your line structure. Use CSI MasterFormat divisions with Load CSI divisions, or the cost codes in your estimate.
  3. 3Split big scopes so progress on each line is visible. Concrete becomes foundations and slabs, for example. Add a row under any line with Enter.
  4. 4Decide how fee and overhead show. Pick Scheduled values or Costs, spread the rest, and tick Keep at cost where a line must not carry fee.
  5. 5Check the balance, then download. The balance bar under the lines says Balanced when the difference reaches zero. Then Download CSV.

The project manual or the architect may require a set format, so check it first.

A Worked Schedule of Values Example

An illustrative $1,380,000 contract sits on $1,230,000 of estimated cost, and bonds and insurance of $30,000 stay at cost. The $150,000 of fee and overhead is spread across the other $1,200,000 of lines, which raises each of them by 12.5 percent.

Illustrative figures
ItemCodeDescriptionCostKeep at costScheduled valueShare of contract
101General conditions$96,000No$108,0007.83%
201Bonds and insurance$30,000Yes$30,0002.17%
303Concrete$200,000No$225,00016.30%
405Metals$160,000No$180,00013.04%
506Wood, plastics and composites$64,000No$72,0005.22%
607Thermal and moisture protection$112,000No$126,0009.13%
708Openings$80,000No$90,0006.52%
809Finishes$168,000No$189,00013.70%
922Plumbing$88,000No$99,0007.17%
1023HVAC$120,000No$135,0009.78%
1126Electrical$112,000No$126,0009.13%
Total$1,230,000$1,380,000100.00%

The lines total $1,380,000, so the schedule balances. The cost column stays in your internal copy, not in the file you send.

Show Fee and Overhead as a Line, or Spread It

Your contract or the architect decides. Some owners want fee and overhead on their own line so they can see it, and others accept it spread across the work in proportion to cost. The template does either and keeps the total equal to the contract sum.

As its own line, it is a line such as Overhead and fee in Scheduled values mode. Spread, it uses Costs, spread the rest. Lines that must stay at cost, such as bonds and insurance or allowances, get the Keep at cost tick. The same overhead and profit decision applies to general conditions, which are often their own line.

As its own line

Concrete$200,000
Metals$160,000
Finishes$168,000
Overhead and fee$66,000
Contract sum$594,000

Spread in proportion to cost

Concrete$225,000
Metals$180,000
Finishes$189,000
Contract sum$594,000

Illustrative. $528,000 of cost plus $66,000 of fee and overhead, 12.5 percent of cost, either way.

Front-Loading and Why a Schedule Gets Sent Back

Front-loading means putting more value on early lines than the work is worth, so the contractor is paid ahead of progress. Kevin O'Beirne's 2022 guidance for the Construction Specifications Institute says reviewers check each line for reasonableness, which "helps reduce the potential for 'front-end loading'", and ask for backup when an amount looks too high or too low.

Other common reasons a schedule comes back, from the same guidance:

  • Lines that do not add up to the contract sum
  • Lines too broad to measure progress on
  • A format different from the one the contract asks for
  • Lines that do not match the cost-loaded schedule, where one is used

In our view, spreading fee in proportion to cost is one simple way to avoid front-loading, because it keeps every line at the same ratio.

When the Schedule of Values Is Due

On AIA A201-2017 contracts with a stipulated sum or a guaranteed maximum price, section 9.2 has the contractor submit the schedule of values to the architect before the first application for payment, allocating the entire contract sum. The project manual usually sets the exact timing and format. The schedule is then used to review each payment request unless the architect objects.

From This Schedule to Monthly Billing

This page builds the schedule at contract award. For monthly billing against the same lines, the pay application template adds work completed, stored materials, retainage and the payment due.

  1. 01 · AT AWARD

    Schedule of values

    This page.

  2. 02 · EVERY MONTH

    Pay application

    Pay application template

If your contract calls for the AIA's own forms, the G703 continuation sheet is licensed from the AIA. See AIA G702 and G703.

What This Template Leaves Out

This template builds and balances the schedule. It does not track billing, payments or later revisions, and it is not the AIA form.

  • No work completed, stored materials or payment columns. Use the pay application template.
  • The retainage column is a plain field. The template does not calculate it.
  • Displayed percentages are rounded, so they can add to 99.99 or 100.01 while the dollars balance exactly.
  • The format your contract requires wins.

This template is a starting point, not legal or accounting advice.

Start From a Priced Estimate

Ruh AI's Estimating Agent prices the takeoff from your own rate book, and a person on your team approves every scope line before Ruh measures it.

Schedule of Values Template FAQs

What should a schedule of values include?+

A line for each part of the work with its dollar value, adding up exactly to the contract sum. Most also show an item number, a cost code or CSI division, a description, and each line's share of the contract, with the project and contract details at the top.

How many lines should a schedule of values have?+

Enough that progress on every line can be seen and agreed in the field, and no more. Split big scopes such as concrete or electrical into parts, and follow any breakdown your project manual requires.

Is this the AIA G703 form?+

No. This is Ruh's own template. The AIA's G703 continuation sheet is licensed from the AIA, so if your contract requires it, use the AIA form. The lines you build here carry over to it.

Do the lines have to add up to the contract sum?+

Yes. Under AIA A201-2017 section 9.2, the schedule of values allocates the entire contract sum. If you use a different contract form, check its payment section for the same rule. The balance bar shows the difference until it reaches zero.

Should overhead and profit be a separate line?+

It depends on your contract and the architect. Some want fee and overhead on their own line, others accept it spread across the work in proportion to cost. The template does both.

What is the difference between a schedule of values and a pay application?+

The schedule of values is built once, at contract award, and splits the contract sum into lines. A pay application is the monthly request for payment that bills progress against those lines. Our pay application template handles the monthly part.

Is the schedule of values template free?+

Yes. Build as many schedules as you like and download each one as a CSV file, built from what you enter.

More tools: Pay Application Template. Free construction tools

This template is a starting point, not legal or accounting advice. Your contract decides the format, the lines and the retainage.