Project delivery methods compared: design-bid-build, CM at risk and design-build
A project delivery method is how an owner contracts for design and construction: who designs, who builds, when the builder joins and how the price is set. Below, six questions show which of design-bid-build, construction manager at risk and design-build fit your project and where each one conflicts, followed by a side-by-side comparison.
Reviewed by the Ruh construction team · November 2026
Calculated with the free project delivery method comparison at ruh.ai
Six Questions About the Project
Answer for the owner. Which answer conflicts with which method is our view, a starting point, not a rule.
Methods against your answers
- Design-bid-build
- bidders need complete documents to price a hard bid
- Design-bid-build
- the price is a lump sum bid, not a guaranteed maximum price
- Design-bid-build
- the builder joins only after the design is finished
- Design-build
- the designer works for the design-builder
- Design-build
- the design-builder makes design decisions to the owner's requirements
CM at risk fits every answer. Use that to start the conversation with the owner, then check it against the contract and the procurement rules that apply.
How This Is Calculated
- Each answer is checked against design-bid-build, CM at risk and design-build. Where a method works against the answer, the tool lists it as a conflict with the reason.
- Fits all six answers lists every method with no conflicts. Nothing is weighted, added up or ranked.
- Which answer conflicts with which method is Ruh's view of how each method usually works, not a procurement rule. Owners, contracts and state laws vary.
Whatever the method, the price starts with quantities. Get a takeoff free.
Send one set of drawings from a job you are bidding and we take it off free, every quantity tied to the sheet it came from.
Design-Bid-Build vs CM at Risk vs Design-Build
The three methods differ in how many contracts the owner signs and when the builder's price becomes firm.
| Design-bid-build | CM at risk | Design-build | |
|---|---|---|---|
| Owner's contracts | Two: designer and contractor | Two: designer and construction manager | One: the design-builder |
| Builder joins | After design, by bidding | During design, by selection | At the start, with the designer |
| Price set | Lump sum bid on finished documents | Guaranteed maximum price, often at design development | Lump sum or guaranteed maximum price, early |
| Design control | Owner, through its designer | Owner, through its designer | Design-builder, to the owner's requirements |
| Overlap of design and construction | None | Possible through early packages | Built in |
| Common AIA agreements | A101 with A201 | A133 with A201 | A141 |
Typical practice. Contracts can be written differently, and ConsensusDocs publishes its own forms for each method.
How Each Method Works
Design-bid-build runs in sequence. The owner's architect finishes the documents, contractors bid them, and the owner usually awards to the lowest responsive, responsible bidder. It gives the clearest price competition and the longest timeline.
Construction manager at risk brings the builder in during design to advise on cost and sequence. Later the construction manager agrees to a guaranteed maximum price and signs the trade contracts.
Design-build puts design and construction under one contract, so one party answers for both and construction can start before design is finished. Progressive design-build sets the price in stages as the design develops, and integrated project delivery shares risk and reward among owner, designer and builder in one agreement.
What Changes for the Estimator
The method decides when the estimate has to be firm and what drawings it is priced from.
| Method | When the price is firm | What it is priced from |
|---|---|---|
| Design-bid-build | On the bid date | Complete documents, as one hard bid |
| CM at risk | At the guaranteed maximum price | Preconstruction estimates at each design release |
| Design-build | Early, then firmed up | A program or concept, often a Class 4 or 5 range |
Typical practice. Class 4 and Class 5 are AACE estimate classes.
More on preconstruction estimates and the AACE estimate classes.
Each one still comes down to quantities taken off the drawings that exist at the time. The construction estimate template works for all three.
Public Owners and Procurement Law
Many public owners must award construction to the lowest responsive, responsible bidder unless a statute lets them do otherwise, which is why design-bid-build is still the default on a lot of public work. Many states now allow CM at risk or design-build for some owners or project types, each with its own conditions. This is typical practice, not legal advice.
Check the procurement law that applies to the owner before choosing a method. The tool flags it when you choose lowest-bidder award.
Our View
For a general contractor the method decides where the money is made and lost. Hard bids reward a tight takeoff on finished documents, CM at risk rewards preconstruction estimates the owner can trust at each design release, and design-build rewards pricing what has not been drawn yet. Pick the work whose risk your estimating team is built to carry.
Project Delivery Method FAQs
What is the difference between design-build and design-bid-build?+
One contract or two. In design-build a single firm designs and builds, so the builder helps shape the design. In design-bid-build the owner's architect completes the drawings first and contractors price them afterward.
What is construction manager at risk?+
It is a method in which the builder joins while the design is under way, prices it as it develops, and then guarantees a maximum price and signs the trade contracts itself.
Is design-build faster than design-bid-build?+
It can start construction sooner, because design and construction overlap under one contract. Whether it finishes sooner depends on the project and how quickly the owner makes decisions.
Can a public owner use design-build or CM at risk?+
Often, but not always. It depends on the state and the owner, since many public owners need specific statutory authority to award anything other than a low-bid contract.
What is progressive design-build?+
It is design-build with the price set in stages. The design-builder is selected mostly on qualifications, develops the design with the owner, and then proposes a price once enough of the design is known.
Is the delivery method comparison free?+
Yes. Answer the six questions, then copy, print or download the result. No account is needed.
More tools: Construction Estimate Template, Construction Bid Proposal Template, General Conditions Calculator. Free construction tools
This comparison is a starting point for planning, not legal or procurement advice. Which answer conflicts with which method is Ruh's view, and the owner's contract and the law that applies decide which methods can be used.