What is AIA G704?

AIA G704 is the American Institute of Architects' Certificate of Substantial Completion. On this page: how G704 relates to G701 and G702, a worked example of its entries, our view, and a free certificate template.

Free 30-minute walkthrough on your own drawings. No card.

Updated November 2026 · Reviewed by the Ruh construction team

The definition

AIA G704, Explained.

The architect prepares a G704 to record the date the work is substantially complete, attaches the list of items left to finish, and the owner and contractor countersign to take on their duties from that date.

G704 is the form behind section 9.8.4 of the AIA A201-2017 General Conditions. It identifies the project and the work covered, states the date of substantial completion, refers to the attached list of items to be completed or corrected, and records who takes on security, maintenance, utilities, damage and insurance. It also states the time allowed to finish the listed items.

Because warranties start on the date it records unless it says otherwise, G704 is one of the most consequential single pages in an AIA closeout.

To record the same facts in a free workbook of our own design, use the certificate of substantial completion template.

How it is measured

A G704 records a date and a list rather than a quantity. What gets tracked after it is signed is the count and value of the open items and the days left to finish them.

G704 vs G702 vs G701

In typical practice, final payment on the last G702 waits until the items listed on the G704 are finished.

Changes run through AIA G701, billing through the AIA G702 and G703, and the milestone itself is substantial completion.

FormWhat it doesWhen
G701 Change OrderChanges the contract sum and timeWhen a change is agreed
G702 Application for PaymentBills the workEach payment period
G704 Certificate of Substantial CompletionMarks the handover date and open itemsAt substantial completion

Our View

Read the responsibilities on the certificate as carefully as the date. Who insures the work and who pays the utilities from that day are easy to leave blank and costly to argue about later.

Worked example

A Worked G704 Example.

Illustrative example. The architect inspects an office build-out and finds it ready for the owner's use on February 19, 2027, with five items open. The certificate is issued on February 22.

Substantially complete on February 19, 2027, issued February 22, five items worth $2,055 to finish within 30 days, by March 21, 2027.

Entry on the certificateValue
Date of substantial completionFebruary 19, 2027
Work coveredEntire work
Items to complete or correct5, attached, worth $2,055
Time to finish the items30 days, so by March 21, 2027
Security and utilities from that dateOwner

Step by step: the five items are $180 + $150 + $1,200 + $450 + $75 = $2,055, and February 19 plus 30 days is March 21.

The certificate details are a sample from Ruh's free template, not a real project.

How Ruh handles it

How Ruh Handles AIA G704.

Try Ruh on a real bid.

Start with a walkthrough

AIA G704: Frequently Asked Questions

What is the AIA G704 form?+

AIA G704 is the Certificate of Substantial Completion: the architect's record of the date the work is substantially complete, with the list of open items and the responsibilities the owner and contractor accept.

Who signs the AIA G704?+

The architect, the contractor and the owner. The architect certifies the date, and the other two sign to accept the responsibilities and the time to finish the listed items.

Is the punch list part of the G704?+

Yes. The list of items to be completed or corrected is attached to the certificate and referenced on it.

Is AIA G704 free?+

No. It is a copyrighted, licensed AIA document. Free certificate templates use their own layout.

What happens after the G704 is signed?+

The owner takes over the responsibilities it lists, warranties start unless it sets another date, and the contractor finishes the listed items within the time allowed before final payment.

Still measuring by hand? Your next takeoff can run while you review this one.

See it on your plans

Related Terms

Keep going: A Worked G704 Example., the free certificate template or explore General Contractor Software.

The Construction Estimating Cheat Sheet
Every unit, waste factor, and conversion on one page. Free PDF.

Figures on this page are illustrative. Construction estimates depend on project-specific conditions, source documents, market pricing, and professional judgment. Ruh's AI assists the estimator and does not replace professional review: your team reviews, validates, and approves every estimate, bid, and pricing decision.

Try Ruh on a Bid You Are Pricing Now.

Put Your Next Takeoff on Ruh.