Certificate of Substantial Completion Template
A certificate of substantial completion is the signed record that a construction project, or a named part of it, is complete enough for the owner to use as intended. On this page: a free Excel certificate with an open items sheet, what the certificate settles, a worked example, and our view on what to check before signing.

What is in the workbook
- Project, owner, contractor, architect, contract date, and whether it covers the entire work or a portion
- Date of substantial completion, open items and their value from the attached list, and the complete-by date
- Responsibilities table for security, utilities, insurance, maintenance and damage, with dates
- Open items sheet that totals the count and value, and signature lines for architect, contractor and owner
Handing this job over? Get the takeoff for your next bid free.
Send one set of drawings from a job you are bidding and we take it off free, every quantity tied to the sheet it came from.
What a certificate of substantial completion settles
The certificate turns a judgment into a date, and a lot hangs on that date. Under AIA A201-2017 section 9.8.4, the certificate sets out the responsibilities of the owner and the contractor for security, maintenance, heat, utilities, damage to the work and insurance, and fixes the time for finishing the listed items. Under the same section, warranties begin on the date of substantial completion unless the certificate says otherwise.
The AIA's own form is G704. Ours is a separate layout, and the AIA G704 glossary entry explains what that form holds.
A worked certificate example
In this illustrative example, an office build-out reaches substantial completion on February 19, 2027, and the certificate is issued on the 22nd. Five punch items are still open, and the contractor has 30 days to finish them.
| Open item | Trade | Value |
|---|---|---|
| Closer adjustment, conference 210 | Doors and hardware | $180 |
| Faucet repair, break room | Plumbing | $150 |
| Replace lifted carpet tiles at the entry | Flooring | $1,200 |
| Rebalance diffuser, office 207 | HVAC | $450 |
| Clean sidelight glass | Glazing | $75 |
| Total, 5 items | $2,055 |
February 19, 2027 plus 30 days is March 21, 2027, the date the listed items are due.
Our view: before anyone signs
In our view, a certificate should not be signed until four things are true.
- The punch list is attached, numbered and agreed. Build it with the free punch list template.
- Each responsibility has a party and a start date, so nothing on site is left uninsured or unlocked.
- The value of the open work is stated, since many owners hold back money against it.
- Permits and any certificate of occupancy the use requires are in hand or listed as open.
The certificate does not end the job. Final completion, and the release of retainage on most contracts, follow once the listed items are done.
Certificate of substantial completion FAQs
What is a certificate of substantial completion?+
It is the signed document that records the date a project, or a named portion, is complete enough for the owner to occupy or use as intended, along with the open items and who is responsible for what from that date.
Who issues a certificate of substantial completion?+
On AIA contracts, the architect prepares it after inspecting the work, and the owner and contractor sign it to accept their responsibilities. Other contracts name their own certifier.
Is this the AIA G704 form?+
No. It is Ruh's own layout. Where a contract calls for G704 itself, sign that AIA document and use this file to track the open items and what they are worth.
When do warranties start?+
Under AIA A201-2017, on the date of substantial completion, unless the certificate sets another date. Other contracts can say otherwise, so check yours.
What is the difference between substantial completion and final completion?+
Substantial completion lets the owner start using the work. Final completion comes later, when every listed item is done, closeout documents are in and final payment is due.
Is the certificate template free?+
Yes. Unlock it with a work email and use it for every project you close out.
This template is not legal advice and not the AIA G704 document. Your contract decides who certifies completion and what follows from the date.