Free construction template
Submittal Log Template
A submittal log is the general contractor's register of every shop drawing, product data sheet, sample and certificate the specification asks for, with where each one stands in review. On this page: a free Excel submittal log that works back submit-by dates, the formula, a worked example, and our view on planning for a resubmittal.

What is in the workbook
- Project setup: default review days per cycle, resubmittal cycles to allow for, subcontractor prep days and an as-of date
- One row per submittal: number, section, type, responsible party, long-lead flag, need date and lead time
- Submit-by and request-by dates calculated, then received, sent, returned, ball in court and action
- Days in review, a late flag in red, and totals for late, in-review and resubmit items
Working from the specs and drawings? Get a free takeoff on your set.
Send one set of drawings from a job you are bidding and we take it off free, every quantity tied to the sheet it came from.
How the submit-by date is worked out
Start from the day the item has to be on site and work backward. Take off the supplier's lead time after approval, then the review time for the first submission and for every resubmission you allow for. What is left is the latest day the submittal can go to the architect.
Submit by = needed on site - lead weeks x 7 - review days x (cycles + 1).
A worked submittal log example
An illustrative log of four submittals on an office build-out, read on October 30, 2026, with 14 review days and one resubmittal cycle by default.
| Submittal | Working | Submit by | Status |
|---|---|---|---|
| Curtain wall, 08 44 13 | Jan 18 - 84 - 28 days | 2026-09-28 | With the architect, 34 days |
| Gypsum board, 09 21 16 | Nov 2 - 42 - 20 days | 2026-09-01 | Approved in 10 days |
| Diffusers, 23 37 13 | Dec 7 - 28 - 28 days | 2026-10-12 | Late, not yet sent |
| Door hardware, 08 71 00 | Jan 25 - 70 - 28 days | 2026-10-19 | Revise and resubmit, 12 days |
Gypsum board uses 10 review days in place of the default. The same four rows are in the workbook.
The diffusers are the first to chase: their submit-by date passed on October 12 and the mechanical subcontractor has not sent them. The curtain wall needs a call too, since it has been with the architect 34 days against a 14-day review. The door hardware needs a second cycle, which is why the log allows for one.
Who reviews a submittal
The contractor reviews a submittal before it goes out, then the architect or engineer reviews it against the design. AIA A201-2017 covers the sequence in section 3.12, and section 3.10.2 has the contractor prepare a submittal schedule. A submittal shows how the contractor will meet the documents. It does not change them, so a difference that matters goes through an RFI or a change order. More in the submittal glossary entry.
Before you send the requests
- Every specification section that asks for a submittal has at least one row.
- Long-lead items sit at the top of the list.
- Each row names the activity it blocks, so a late submittal shows its cost to the schedule.
- Need dates come from the current schedule. The construction schedule template gives them by activity.
Our view: plan for the resubmittal
In our view, every long-lead submittal should be scheduled as if it will come back once. The door hardware in the example did, and because the log allowed for a second cycle, its submit-by date already had room for it.
Submittal log template FAQs
What is a submittal log in construction?+
A submittal log is the register of every submittal the specification requires, such as shop drawings, product data and samples, with who owes it, when it is due, where it is in review and what action came back.
What does ball in court mean on a submittal log?+
Ball in court names the party who has to act next: the subcontractor preparing it, the general contractor checking it, or the architect or engineer reviewing it.
How many review days should a submittal log allow?+
Whatever the specification's submittal procedures section states. If it is silent, agree a number at the start and allow for at least one resubmission on anything long lead.
What is the difference between a submittal log and a submittal schedule?+
A submittal schedule sets when each submittal is due. A submittal log tracks each one after that, through review to its final action. This template does both on one row.
Does an approved submittal change the contract?+
No. An approved submittal shows how the contractor will meet the contract documents. A change to the documents still needs a change order.
Is the submittal log template free?+
Yes. Enter a work email, the file unlocks, and the log has room for 400 submittals.
This template is a tracking tool, not legal advice. Your specification sets the submittal types, review times and procedures.