Self-perform vs subcontract calculator
Self-performing means a general contractor builds a scope with its own crews instead of buying it from a subcontractor. Below: the calculator, how to compare the two, a worked comparison, the break-even, what each side carries, and our view.
Reviewed by the Ruh construction team · November 2026
Calculated with the free self-perform vs subcontract calculator at ruh.ai
The Scope
One scope at a time, in the unit you price it in. Every default here is illustrative.
Self-Perform
Subcontract
Self-perform or subcontract
- Labor, 420 hours
- $19,173.00
- Material, equipment and supervision
- $48,500.00
- Self-perform contingency
- $3,383.65
- Subcontractor's quote
- $78,000.00
- Sub bond or default insurance
- $936.00
- Coordination and management
- $2,340.00
- Scope gap allowance
- $1,560.00
Self-performing is $11,779.35 lower on these inputs. The two break even at $72.36 an hour, or at 0.0555 labor hours per unit at your rate.
How This Is Calculated
- Labor: quantity x labor hours per unit x burdened labor rate.
- Self-perform, all in: (labor + material + equipment + supervision) x (1 + contingency %).
- Subcontract, all in: quote + quote x (bond or default insurance % + coordination % + scope gap %).
- Break-even labor rate: (subcontract all in / (1 + contingency %) minus material, equipment and supervision) / labor hours.
- Break-even labor hours per unit: the same amount / (quantity x your burdened labor rate).
Deciding what to self-perform? Get the quantities from your own drawings, free.
Send one set of drawings from a job you are bidding and we take it off free, every quantity tied to the sheet it came from.
How to Compare Self-Performing With Subcontracting
Compare like with like: both sides priced for the same scope, with the costs each one carries that the other does not.
- 1Take the quantity of the scope from a takeoff of the drawings, not from an allowance.
- 2Price self-performing: quantity x labor hours per unit x your burdened rate from the labor burden calculator, plus material, equipment, supervision and a contingency for production risk.
- 3Price subcontracting: the leveled quote, plus the sub's bond or default insurance, your coordination time and an allowance for what the quote leaves out.
- 4Compare the two totals, then check how far your production can slip before the sub is cheaper.
A Worked Self-Perform Comparison
On an illustrative 12,000 unit scope, your crew costs $71,056.65 all in against $82,836.00 for the subcontractor, so self-performing is $11,779.35 lower. These are the calculator's defaults.
| Line | Self-perform | Subcontract |
|---|---|---|
| Labor, 420 hours at $45.65 | $19,173.00 | |
| Material, equipment and supervision | $48,500.00 | |
| Self-perform contingency, 5% | $3,383.65 | |
| Subcontractor's quote | $78,000.00 | |
| Sub bond or default insurance, 1.2% | $936.00 | |
| Coordination and management, 3% | $2,340.00 | |
| Scope gap allowance, 2% | $1,560.00 | |
| All in | $71,056.65 | $82,836.00 |
Illustrative figures, not a customer job. 420 hours is 12,000 units x 0.035 hours per unit.
Reading the Break-Even
The break-even shows how much room the decision has. In the example the two sides cost the same at $72.36 an hour, or at 0.0555 labor hours per unit at your $45.65 rate.
Your crew could use about 59 percent more labor hours per unit than planned before the subcontractor became cheaper. A thin margin, say a break-even only 10 percent above your planned production, means one bad week decides the scope, and the sub's fixed price is worth paying for.
What Each Side Carries
| Cost | Self-perform | Subcontract |
|---|---|---|
| Labor and production risk | Yours | In the sub's price |
| Material and equipment | Yours to buy and manage | In the sub's price, unless excluded |
| Supervision | Your foreman's time on this scope | Your coordination time |
| Default risk | None | A sub bond or default insurance |
| Scope gaps | None, you build what is drawn | Whatever the quote leaves out |
Typical practice. Your contract and the quote decide the real split.
Our View
Self-perform the scopes where you know your production from your own job cost history and the crew would otherwise sit idle. Buy the rest. A self-perform price built on a guessed production rate is a subcontract you sold yourself without the fixed price.
More on the decision in the self-perform work glossary entry.
Self-Perform vs Subcontract FAQs
What does self-perform mean in construction?+
It means a GC builds the scope itself, with people on its own payroll and its own equipment, instead of buying it from a trade contractor. Concrete, carpentry and general labor are common examples.
Is self-performing cheaper than subcontracting?+
Only when your crew's production and burdened rate beat the sub's quote with its bond, your coordination and the scope gaps added. The calculator shows the margin either way.
Where do labor hours per unit come from?+
From your own job cost reports: hours charged to a cost code divided by the quantity installed. Published production rates are a fallback, not a substitute.
Which costs get missed when self-performing?+
The ones the sub's quote hid: supervision time, small tools, equipment idle time, rework and the contingency for a crew that runs slower than planned.
Is the self-perform vs subcontract calculator free?+
Yes, free and with no login. Both sides of the comparison download as one CSV.
More tools: Labor Burden Calculator, Bid Tabulation Template, Construction Estimate Template. Free construction tools
This calculator compares the costs you enter for planning and pricing. It is not a guarantee of cost or production, and your contract, insurer and own job history decide the real figures.