100% money-backBook a walkthrough
Free construction tool

Masonry calculator: CMU and brick units, mortar, and grout

Enter wall length, height, and the openings you are deducting, then get net wall square footage, block or brick counts, mortar bags, and grout volume. Every step is printed under the results, and the 1.125 units per square foot rate is derived below rather than asserted.

Net wall area
540 sf
Units to order
638
Mortar (80 lb bags)
38
Grout (cu ft)
32.9
Every step
Gross wall area
60 ft x 12 ft = 720 sf
Openings deducted
180 sf
Net wall area
540 sf
Quantified on
net area = 540 sf
Unit rate
1.125 units per sf (8 x 16 nominal face)
Units laid
540 x 1.125 = 607.5
Units to order at 5 percent waste
638 ea
Mortar
607.5 / 16 units per bag = 38 bags (80 lb preblended)
Grout at 48 in o.c.
5.4 x 6.1 cf per 100 sf = 32.9 cf (1.22 cy, 50 bags)

Formula: net wall area = (length x height) minus openings deducted. Units = area x units per sf, where 8 x 16 nominal CMU is 144 / 128 = 1.125 per sf and modular brick is 144 / 21.333 = 6.75 per sf. Mortar bag yields (16 conventional CMU or 50 brick-sized units per 80 lb preblended bag) and grout volumes per 100 sf are NCMA TEK 4-2A Tables 2 and 3; the grout table assumes two-core hollow units and carries 3 percent waste. Brick mortar cubic feet are BIA Technical Notes 10 Table 4, net of waste, so add BIA's 15 to 25 percent mortar waste allowance before ordering. Grout is only in scope where the reinforcing schedule actually calls for grouted cells. Bond beams, lintels, control joints, flashing, and reinforcing are separate line items.

Email me these numbers

Get your numbers in writing. A human follows up within one business day, no spam.

100%

Try Ruh on a real bid. 100% money-back guarantee if you are not satisfied.*

*Scoped delivery, terms apply. Read the guarantee terms

Start with a walkthrough

How masonry square footage is actually taken off

Masonry is taken off as square feet of wall face, separately for every unit type and every wall thickness, then converted to units with a rate per square foot. You scale each wall for length off the plan and for height off the sections or elevations, multiply, deduct the openings, and stop. The conversion from area to block or brick is arithmetic. The judgement is all in how you segmented the walls and what you did with the openings.

Segment by wall type, not by elevation. A single wythe 8 in CMU wall and a CMU backup carrying brick veneer cover the same square feet of elevation and are nowhere near the same money. Corners, returns, jambs, control joints, lintels, and bond beams come off in linear feet as separate lines, because they do not scale with area.

The formulas

Gross wall area (sf) = wall length (ft) x wall height (ft) Net wall area (sf) = gross wall area minus openings deducted Units laid = wall area (sf) x units per sf Units to order = units laid x (1 + waste percent / 100) CMU mortar (80 lb preblended bags) = units laid / 16 Brick mortar (cu ft) = (brick laid / 1,000) x cubic feet of mortar per 1,000 brick Grout (cu ft) = (wall area / 100) x cubic feet of grout per 100 sf of wall Grout (cu yd) = grout cubic feet / 27, and grout bags = grout cubic feet / 0.66

Why standard CMU is exactly 1.125 units per square foot

Derive it rather than take it on faith. A standard block is nominally 8 in high by 16 in long on its face, so that face covers 8 x 16 = 128 square inches. A square foot is 12 x 12 = 144 square inches. One square foot of wall therefore takes 144 / 128 = 1.125 units, which is 112.5 units per 100 square feet.

It comes out exact because the dimension is nominal. The unit itself is manufactured 7 5/8 in by 15 5/8 in, and the 3/8 in mortar joint at the bed and the head makes up the missing quarter inch in each direction. Unit plus joint equals the 8 by 16 module, so you divide a square foot by the module rather than by the block. That is also why the rate does not change with wall thickness: a 12 in block still presents an 8 by 16 face.

Modular brick works the same way. A modular brick face is nominally 2 2/3 in high by 8 in long, so 8 x 2.6667 = 21.333 square inches, and 144 / 21.333 = 6.75 brick per square foot, or 675 per 100 square feet.

Now cross-check both against the published tables. NCMA TEK 4-2A Table 1 lists 119 conventional 8 x 16 units per 100 square feet and states that the figure includes about 5 percent waste: 112.5 x 1.05 = 118.1, which rounds to their 119. BIA Technical Notes 10 Table 4 lists 675 modular brick per 100 square feet not including waste, and separately says to add at least 5 percent for breakage: 6.75 x 1.05 = 7.09 per square foot. That is where the field figure of 7 brick per square foot comes from, and it is why you will see 6.75 and 7 quoted for the same wall by people who are both right.

The published rates this calculator uses

  • CMU units: 1.125 per sf, derived above. NCMA TEK 4-2A, Estimating Concrete Masonry Materials, Table 1 gives 119 units per 100 sf with about 5 percent waste included.
  • Modular brick: 6.75 per sf. BIA Technical Notes 10, Dimensioning and Estimating Brick Masonry, Table 4 gives 675 per 100 sf, not including waste.
  • Brick mortar: BIA Technical Notes 10, Table 4, modular brick: 8.1 cu ft per 1,000 brick at a 3/8 in joint, which is 5.5 cu ft per 100 sf of wall, and 10.3 cu ft per 1,000 at a 1/2 in joint. Both are theoretical quantities that exclude waste.
  • CMU mortar: NCMA TEK 4-2A, Table 2: one 80 lb bag of preblended mortar lays about 16 conventional units and one 3,000 lb bulk bag lays about 420. For site mixing, the same table gives about 240 units per ton of masonry sand, and one 70 lb bag of masonry cement lays about 30 units. All of these assume face shell bedding, which is why they do not change with unit width.
  • Grout: NCMA TEK 4-2A, Table 3, cubic feet of grout per 100 sf of wall for two-core hollow units, with 3 percent waste included. For 8 in units: 36.1 with every cell grouted, 18.1 at 16 in on center, 12.1 at 24 in, 9.1 at 32 in, 7.3 at 40 in, and 6.1 at 48 in. Wider units take more, so a 12 in wall at 48 in on center is 9.9.
  • Grout bag yield: NCMA TEK 4-2A: an 80 lb bag of preblended grout yields about 0.66 cu ft. Bond beam grouting is a separate quantity, and TEK 4-2A Table 5 gives about 2.0 linear feet of 8 in bond beam per 80 lb bag.
  • Waste: BIA Technical Notes 10 says to add at least 5 percent to net brick quantities for breakage and waste, and 15 to 25 percent to net mortar quantities. NCMA TEK 4-2A Table 1 has about 5 percent built into its unit counts already, so do not add 5 percent to a number that already carries it.

What the clean square footage misses

Openings deductions are handled inconsistently between bidders. Deducting every opening in full, deducting nothing on the argument that jambs and heads still cost labor, and deducting only openings above a stated size are all in use on real bids. So two masons can submit different square footages for the same elevation without either of them making an arithmetic error, and the general contractor leveling the bids cannot see why the numbers differ. State the rule. Put the deduction basis, the opening count, and the total area deducted into your clarifications. This calculator makes the choice explicit with a deduction rule selector, and it prints gross and net so you can quote either basis and say which one you used.

Waste varies by bond pattern and by how cut up the elevation is. The 5 percent that BIA and NCMA build into their tables is a floor for a plain running bond wall, not a number to carry onto a job full of soldier courses, rowlock sills, header courses, and short returns. BIA Technical Notes 10 Table 6 quantifies part of this for brick: common bond with full headers every fifth course adds one fifth to the brick count and one fifteenth to the mortar. The rest of it, the breakage and the cutting, is shop specific. Pull the ordered quantity against the taken off quantity on your last several jobs and use that spread. Do not adopt anyone else's single percentage, including ours.

Grout is only in scope where cells are actually reinforced, and that is a specification question rather than a geometry question. Grout quantity does not move with wall area. It moves with the vertical bar spacing on the reinforcing schedule and with the bond beam schedule, and both of those live on the structural sheets rather than the architectural elevations. Here is the arithmetic that catches people. Change an 8 in wall from 48 in on center to 24 in on center and the square footage does not move at all, but grout goes from 6.1 to 12.1 cubic feet per 100 square feet, so it roughly doubles. Go solid grouted and it is 36.1, about six times the 48 in on center quantity. Read the S sheets and the masonry specification before you put a grout number in a bid, then say in the proposal what bar spacing and grouted cell count you priced.

Worked example

Take the calculator defaults: one 60 ft long by 12 ft high wall of 8 in CMU, 180 sf of openings deducted (six windows at 5 ft by 6 ft), vertical bars at 48 in on center, and 5 percent unit waste.

Gross wall area is 60 x 12 = 720 sf. Deduct the 180 sf of openings and the net area is 540 sf. At 1.125 units per square foot that is 540 x 1.125 = 607.5 units laid, and adding 5 percent waste gives 638 units to order. Mortar covers the units actually laid, so 607.5 / 16 = 38 bags of 80 lb preblended mortar. Grout at 48 in on center in an 8 in wall is 6.1 cubic feet per 100 square feet, so 5.4 x 6.1 = 32.9 cubic feet, which is 1.22 cubic yards or 50 bags of 80 lb preblended grout.

Switch the same wall to modular brick veneer and only the unit rate changes: 540 x 6.75 = 3,645 brick laid, 3,828 brick to order at 5 percent waste, and mortar of 3,645 / 1,000 x 8.1 = 29.5 cubic feet at a 3/8 in joint, or 73 bags of 80 lb preblended mortar at the TEK 4-2A brick-sized unit yield. Add BIA's 15 to 25 percent mortar waste on top of the 29.5 cubic feet before you order. Grout is not in that scope unless the backup wall is yours as well.

From quantity to a priced line

The block count, the mortar, and the grout are the quantity half of a masonry bid. The priced line multiplies each quantity by your own unit cost for material, mortar and grout, scaffolding, and layup labor, at your own productivity. That is the step Ruh automates. It reads the drawing set, measures the scope wall by wall, and prices the measured quantities against your own price book, with every line traceable back to the sheet it came from, and your estimator reviewing the result before it goes out.

For the unit itself see the CMU glossary entry, and for the scope boundaries that decide whether the grout, the lintels, and the cavity flashing are even yours, read how to bid masonry as a subcontractor.

Masonry calculator FAQs

How many blocks are in a square foot of wall?+

A standard 8 x 8 x 16 concrete block covers 1.125 units per square foot of wall face. The arithmetic is exact rather than a rule of thumb: the nominal face is 8 in by 16 in, which is 128 square inches, and a square foot is 144 square inches, so 144 divided by 128 is 1.125. That is 112.5 units per 100 square feet. NCMA TEK 4-2A Table 1 publishes 119 per 100 square feet, which is the same figure with about 5 percent waste already built into it.

How many bricks per square foot of wall?+

Modular brick runs 6.75 per square foot of single wythe wall in running bond, from the same nominal module arithmetic. A modular brick face is 2 2/3 in by 8 in, which is 21.333 square inches, and 144 divided by 21.333 is 6.75. BIA Technical Notes 10 Table 4 publishes it as 675 brick per 100 square feet, not including waste. BIA also says to add at least 5 percent for breakage, which lands at 7.09 per square foot, and that is where the field figure of 7 brick per square foot comes from.

How much grout does an 8 in CMU wall need?+

It depends entirely on how many cells are actually reinforced, which is a specification question rather than a geometry question. NCMA TEK 4-2A Table 3 gives cubic feet of grout per 100 square feet of wall for two-core hollow units, with 3 percent waste included. For 8 in units that is 36.1 cubic feet with every cell grouted, 18.1 at 16 in on center, 12.1 at 24 in, 9.1 at 32 in, and 6.1 at 48 in. Bond beam grouting is additional and comes off the reinforcing schedule on the structural sheets.

Do you deduct openings from masonry square footage?+

Sometimes, and that inconsistency is the problem. Deducting openings in full, deducting nothing because jambs and heads still cost labor, and deducting only openings above a stated size are all in use, so two bidders can hand in different square footages for the same elevation with neither one making an arithmetic error. The fix is not picking the right rule, it is writing the rule you used into your clarifications so the general contractor can level your number against the others. State the deduction basis, the opening count, and the total area deducted.

Ruh does this for the whole drawing set.

AI takeoff reads your plans, measures every wall type, and prices the quantities on your price book.

More tools: concrete calculator and rebar calculator

Figures on this page are illustrative. Construction estimates depend on project-specific conditions, source documents, market pricing, and professional judgment. Ruh's AI assists the estimator and does not replace professional review: your team reviews, validates, and approves every estimate, bid, and pricing decision.